Fairfax Bridges Project

Town of Fairfax, CA

  • Home
  • The Projects
    • Bridge Preventive Maintenance Program
    • Creek Road Bridge
    • Meadow Way Bridge
    • Azalea Avenue Bridge
  • Events & News
  • Downloads
  • Get Involved

Azalea Avenue Bridge

DSC_0005The existing Azalea Avenue Bridge (State Br. No. 27C-0124) was reportedly constructed over Fairfax Creek in 1930. The cast-in-place reinforced concrete (CIP/RC) T-beam structure is a simple span bridge, nearly 12 feet above the creek bed. It is approximately 31 feet long and 30 feet wide, and was designed to accommodate two narrow lanes of traffic, with a sidewalk on each side.

There are no original design and construction plans available. The bridge is not a historic structure by determination of the State Historic Preservation Officer (SHPO).

Current Conditions

DSC_0011Over the years, the bridge has weathered major damage and large pieces of concrete from several of the load bearing girders have spalled off, exposing damage to the main steel reinforcements. As a result, the bridge has been closed to two-way traffic and trucks over 3 tons; only one-way traffic is allowed, though Azalea Avenue is otherwise a two-way street.

The bridge has a Sufficiency Rating (SR) of 64.6 and was flagged as Functionally Obsolete (FO) by Caltrans in the 2014 Bridge Inspection Report (BIR). These significant bridge rating and structural deficiencies have made it eligible for replacement.

June 13, 2007 024

The existing bridge is also hydraulically inadequate and a contributor to flooding hazards in Fairfax. The current Marin County Flood Control Zone 9 hydraulic studies for the 100-year flood event and FEMA’s Flood Insurance Rate Map (FIRM) show the bridge being under pressure flow and being overtopped because it does not provide an adequate waterway opening for such high-stage flows. The bridge’s inadequacy during high flows has been demonstrated by two major storm events in the area over the past 30 years.

The Project

According to the latest Caltrans BIR, the bridge’s current average daily traffic (ADT) count is 110. Therefore, the new bridge plans call for two 9-foot wide lanes and two 2-foot wide shoulders (a total vehicle travelway width of 22 feet, striped as two 11-foot wide lanes), along with a 4-foot sidewalk and concrete barrier on each side (a total width of 33.5 feet).

The creek is a narrow at the bridge site, and is immediately abutted by adjacent residential properties on the east side, and Arroyo Road on the west side. Retaining walls in the creek will protect the private properties and Arroyo Road and will connect directly to the four corners of the new bridge. Additional drainage infrastructure, such as storm drain pipes through the bridge abutments, will be considered. Bridge aesthetic concepts, landscape architecture and bridge lighting will be incorporated in the design.

Community input received throughout the project development process will be considered by the Town Council in the final design of the bridge. A preliminary concept for the new bridge has been considered: a single span, CIP/RC slab bridge that uses no piers in the waterway with two concrete abutment supports, similar to the existing elements. The concept bridge calls for a span of approximately 42 feet, which is longer than the existing bridge to provide an adequate creek flow area. The bridge deck profile could be raised slightly for better flow conveyance and freeboard above the design flows. A short segment of the approach roadway on each side of the bridge, as well as a short stretch of Arroyo Road at one end of the bridge, will be part of the project.

Funding

Because of the bridge’s deficient structural condition, the age of the structure, and the contribution to flooding hazards, the Town of Fairfax has received federal funding to replace the bridge with a functionally, structurally and hydraulically sufficient bridge.

Construction and Project Schedule

Construction will require a temporary road closure and traffic detour at the bridge site, at the intersection of Azalea Avenue and Arroyo Road. Utilities will be secured and maintained in place prior to removing the existing bridge. Construction will be done during the dry season when the creek is at its lowest flow rate and during the environmentally permissible window (April 15 through October 15). Old debris and drift will be removed, sand bars impeding the water flows will be leveled, and additional cleaning will take place in the bridge area.

DSC_0022The project will go through a full National Environmental Policy Act (NEPA) and California Environmental Quality Act (CEQA) environmental studies and regulatory permitting. Public presentations and workshops are planned during the environmental, design and construction phases of the project. The design and environmental process are expected to take approximately 30 months, and construction will take nearly 12 months, once each phase of the project is funded.

The Town of Fairfax is currently in the process of selecting the design and environmental consulting team.

Immediate Next Steps

The Town of Fairfax is currently selecting a team to complete preliminary engineering, environmental and design services for the Azalea Avenue Bridge.

October 13, 2016: The initial contract for preliminary design and environmental phases of the bridge replacement project was approved by the Town Council in September and executed on September 15, 2016/ Survey crews will be on site to begin field work in early October, and more details about initial project work are available in the following document.

Updates

Project updates and meeting notices will be provided on this website and shared with the project email list (sign up at right).

2016

  • October 13, 2016: The initial contract for preliminary design and environmental phases of the bridge replacement project was approved by the Town Council in September and executed on September 15, 2016/ Survey crews will be on site to begin field work in early October, and more details about initial project work are available in this document: Azalea Avenue Bridge Replacement Update – 101316 (PDF)

Updates and Events

 

  • July 2024
    Town Hall Updates
  • April 2024
    Meadow Way Update
  • September 2023
    Town Hall Updates
  • October 2022
    Meadow Way Email
  • June 2022
    New documents available for download:
    – Chain Docs North of Meadow Way
    – Chain of title exhibit
    – Lee Oberkamper review of chain of title report 22.02.03
    – Marin Land Title Report – 2021.12.09
    – Neighborhood Update Letter June 15, 2022
    – Ownership and Easement Docs for Meadow Way
  • August 2021
    Meadow Way Email
  • June 2020
    On Wednesday, June 3, the Town of Fairfax Council unanimously adopted the CEQA document for the project. The following three documents are a result of that process and finalize the CEQA document’s acceptance by the Town of Fairfax.
    – Meadow Way CEQA Notice of Exemption (NOE)
    – 
    Meadow Way CEQA Notice of Determination (NOD)
    – Resolution-2020-17, Meadow Way Bridge
  • May 2020
    New document available for download:
    – 2020 Meadow Bridge Inspection Report
  • March 2020
    New documents are available for download:
    – Meadow Way PowerPoint CEQA_NEPA – an overview of WRA’s environmental studies, presented to the Town Council on 3/4/20.
    – CIC Presentation 3-4-20 Ver 2 – CIC’s documentation, presented to the own Counil on 3/4/20.
    The decision for adoption of the Initial Study/Mitigated Negative Declaration (IS/MND) has been extended to the next regularly scheduled Town Council meeting on Wednesday, April 1st.  All interested neighbors and members of the public are invited to attend.
  • February 2020
    – Meadow Way Final Initial Study (IS) Mitigated Negative Declaration (MND) document for public review
    – Appendices to Meadow Way Final IS MND
    – Fairfax Town Council Notice of Public Hearing-Meadow Way CEQA
    – 1-24-20 State Clearinghouse MND documentation for Meadow Way Bridge
  • December 2019
    – Meadow Way Notice of Availability (NOA) of the California Environmental Quality Act (CEQA) document for Public Review
    – Initial Study/Mitigated Negative Declaration for the Meadow Way Bridge Replacement Project
    – 
    Meadow Way National Environmental Policy Act (NEPA) Categorically Exempt Document, approved by Caltrans
  • August 2019
    New documents are available for download:
    – Meadow Way Status Update August 2019
    – 07-08-19 NOAA Letter re Meadow Way Bridge
    – 
    MW Bridge NMFS Biological Ltr Signed
    – 
    E-76 Meadow Feb 2019
    – 
    Exhibits 6-D & 6-B for APE & Revetment March 27
    – 
    MW TC Jan 2018 Project Staff Report
  • February 2018
    Your comments and questions have been answered. Visit the Meadow Way Bridge page to read the team’s responses.
  • December 2017
    A new retaining wall is proposed that will create a better fish habitat. Visit the Meadow Way Bridge page to read more and to take a survey.
  • April 2017
    Fire trucks can now cross Meadow Way Bridge. Visit the Meadow Way Bridge page to learn more.

Sign Up for Updates


Sign up to receive updates and find out what's new with the Fairfax Bridges Project!

Your Name (required)

Your Email (required)

Add me to the email list for the Town of Fairfax?

Yes

To prove you are a human, type the answer to this math quiz:

Questions?


Email:
info@fairfaxbridges.com

Phone:
Meghan or Aliza
415-284-1544

Copyright © 2025 · Town of Fairfax, California